Over 1 GW Of Indian Wind Projects Face Slow Execution

It is learnt that, the developers of many of the projects contracted in India’s two wind auctions held in 2017 have missed their commissioning deadlines, with less than 1 GW completed of a total of 2 GW. Only 690 MW of the first 1050MW lot and just 200 MW of the second 1000MW auction held by the Solar Energy Corporation of India (SECI) are constructed. The respective deadlines were October 2018 and May 2019.